Ridley Bendigo
In 2020, LGPM completed its largest project to date; a green field Monogastric Feed Mill in Bendigo, capable of producing an efficient 90 Tonnes per Hour.
The project encompassed the design, construction, and commissioning of the entire production process. Key stages included the raw materials intake, ingredients storage & addition, mixing, pelleting, and out loading.
LGPM designed and engineered all the process equipment and supporting structures, completing the world-class plant in 18 months.
The plant incorporates 36 Mighty Bulk Silos, which boast the heaviest galvanising available worldwide at 600g/m2, making them perfect for the harsh Australia conditions.
A full time-lapse of the project may be seen here
The project encompassed the design, construction, and commissioning of the entire production process. Key stages included the raw materials intake, ingredients storage & addition, mixing, pelleting, and out loading.
LGPM designed and engineered all the process equipment and supporting structures, completing the world-class plant in 18 months.
The plant incorporates 36 Mighty Bulk Silos, which boast the heaviest galvanising available worldwide at 600g/m2, making them perfect for the harsh Australia conditions.
A full time-lapse of the project may be seen here
What’s Happening At LGPM Process Innovation?
We are committed to being more than a bulk materials handling and processing company; we aim to be thought leaders in our industry by providing our clients with continuous insight, sharing the latest trends and communicating updates on technology, safety standards and regulations.